PH: 07 3823 5870

2012 Projects

ST EDWARD’S PRIMARY SCHOOL – Chatswood Road, Daisy Hill

Works undertaken (2012) - Air Conditioning installed in the New Admin & Staff Area. The use of Mitsubishi multi- split systems with cassette type head units gave the perfect solution for this job. It also enabled us to fit a 10kW ducted system into the multi system. No other brand can give this flexibility at a budget price.

Types of systems used:

  • 2 x 14.5 kW Mitsubishi reverse cycle inverter Multi-System
  • 1 x 14 kW Mitsubishi reverse cycle inverter Cassette type system
  • 1 x 2.5 kW Mitsubishi Split system

horizontal spacer

ST PATRICKS COLLEGE - Townsville

Works undertaken (2012) - Air conditioning installed in the Admin & Staff Room. This was a renovation of a very old admin area. The challenge was removing the old systems while trying to resuse what we could for the new layout, this also helped the budget. The Daikin units were the perfect solution and will give significant reduced energy consumption compared to the previous set up.

Types of systems used:

  • 2 x Daikin 20 kW reverse cycle ducted system
  • 1 x Daikin 10.9 kW reverse cycle ducted system
  • 1 x Daikin 24.5 kW reverse cycle ducted system

horizontal spacer

Our Saviour's College - Toowoomba

Works undertaken (2012) - Air Conditioning to the new admin area and server room using Daikin systems. This was a design & construct job that was quite difficult due to the lack of ceiling space and structural beams from the level above. The use of two long solid duct runs and putting balancing dampers near the outlets due to solid set ceiling helped over come air flow issues. The removal of a fixed glass pane and replacing it with a new weather proof louver allowed us to connect fresh air directly to the return air.

Types of systems used:

  • 2 x Daikin 20 kW reverse cycle inverter split ducted systems
  • 1 x Daikin 3.5 kW Split System

horizontal spacer

Our Lady of the Way Catholic School – Armstrong Street, Petrie

Works undertaken (2012) - Air conditioning to the new GLA's. This was a simple design and construct job that had the two separate classrooms served via Reverse cycle inverter cassette units.

Types of systems used:

  • LG 12.5 kW reverse cycle inverter Cassette Systems

horizontal spacer